Works Package 2 lot 2: Dunga Lake Intake, Water Treatment Plant and Nyalenda Ponds

Project Detail Report

Overview

StatusProposed
TypeWater Supply
AgencyLake Victoria South Water Works Development Agency
ProgramLake Victoria Water and Sanitation (LVWATSAN) Program
Progress0.00%

Location Information

CountyKisumu
ConstituencyKisumu Central
WardNyalenda B
SettingUrban
Coordinates-0.125814, 34.741494

Timeline & Impact

Start Date2025-02-11
Planned End DateN/A
Actual End DateN/A
ContractorFeasibility Study Ongoing
ConsultantBRL/SCET Tunisie/ISEP
Target AreasDunga water treatement plant and Intake
Scope of WorksReplacement of pumps Reconstruction of water reservoirs Water treatment Process works
ImpactsMore water production Efficient power consumption Improved quality of treated water
ChallengesYet to start
RemarksFeasibility Studies Ongoing

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 118,133,924.80
Afd Loan 425,282,129.30
Eib Loan 756,057,118.70

Beneficiaries

Target Households45,000
Target Population200,000