Overview
| Status | Proposed |
| Type | Water Supply |
| Agency | Lake Victoria South Water Works Development Agency |
| Program | Lake Victoria Water and Sanitation (LVWATSAN) Program |
| Progress | 0.00% |
Location Information
| County | Kisumu |
| Constituency | Kisumu Central |
| Ward | Nyalenda B |
| Setting | Urban |
| Coordinates | -0.125814, 34.741494 |
Timeline & Impact
| Start Date | 2025-02-11 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Feasibility Study Ongoing |
| Consultant | BRL/SCET Tunisie/ISEP |
| Target Areas | Dunga water treatement plant and Intake |
| Scope of Works | Replacement of pumps
Reconstruction of water reservoirs
Water treatment Process works |
| Impacts | More water production
Efficient power consumption
Improved quality of treated water |
| Challenges | Yet to start |
| Remarks | Feasibility Studies Ongoing |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
118,133,924.80 |
| Afd |
Loan |
425,282,129.30 |
| Eib |
Loan |
756,057,118.70 |
Beneficiaries
| Target Households | 45,000 |
| Target Population | 200,000 |