| Start Date | 2024-05-09 |
| Planned End Date | 2028-01-11 |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | CES/MIBP |
| Target Areas | Kitutu Central, Kisii Central, Bobaracho |
| Scope of Works | Water Supply: • Replacement of 31 km old / dilapidated pipes & appurtenances. • Extension of water reticulation system, |
| Impacts | Improved sanitation; Improved hygiene; Reduced water-borne diseases; Increased coverage to portable piped water supply |
| Challenges | Frequent blockages in sewers due to solid waste deposition in sewer chambers (Poor management of solid wate); Sewer lines passing through private lands & properties; Encroachment of sewer wayleaves in some areas; Existing sewer lines that have not been connected to clients |
| Remarks | Project ongoing smoothly; Works Contract expected to be signed before January 2029 |