| Start Date | N/A |
| Planned End Date | 2024-12-11 |
| Actual End Date | 2025-11-04 |
| Contractor | Smooth Engineering Construction Conmpany Limited |
| Consultant | N/A |
| Target Areas | Kabianga, Kapcheluch and Kibingei Sub-locations |
| Scope of Works | Construction of 2,000 m3 WTP, Construction of 3 No. water kiosks, Intake works on R. Kabianga, Construction of Raw and Treated water Rising Main, Laying of 9km distribution lines, Construction of 200 m3 elevated storage tank, Electro-mechanical works |
| Impacts | Improve reliability of safe, treated and reliable water. Reduce waterborne diseases |
| Challenges | Delayed disbursements of funds |
| Remarks | Project is ongoing with construction of the intake on River Kabianga |