| Start Date | 2020-06-10 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Mabota Investment Limited |
| Consultant | N/A |
| Target Areas | Kapkusum Primary School, Kalyet centre, and the sorrounding community members |
| Scope of Works | Borehole drilling, equipping of borehole with solar panels and solar powered pumpset, construction of 3nr water kiosks, rising main water lines, distribution pipelines, 60m3 Composite FRP Tank on a 6M High Elevated Steel Tower. |
| Impacts | Provision of reliable clean and potable water supply to the school enchancing hygiene and sanitation, improvemet in overall school performance |
| Challenges | Shading as the area experiences extended periods of rainy seasons |
| Remarks | Complete and operational |