Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Progress
33.00%
Location Information
County
Mombasa
Constituency
Changamwe
Ward
Kipevu
Setting
Urban
Coordinates
-4.005740, 39.613070
Timeline & Impact
Start Date
N/A
Planned End Date
N/A
Actual End Date
N/A
Contractor
Njuca Consolidated Company
Consultant
Interconsult Engineers Ltd
Target Areas
Magongo, Mainland, Bomu
Scope of Works
· Construction of 15km Secondary and Tertiary sewer lines Pipelines Diameters ranging from 160-400 mm 300 manhole chambers. Rehabilitation of 800m Trunk Mains.
Impacts
Stalled
Challenges
33% Progress The project has a pending litigation. Out of court settlement is being considered