Rehabilitation of the Kipevu wastewater treatment system and pumping stations

Project Detail Report

Overview

StatusOngoing
TypeRehabilitation of Fecal Sludge Treatment Plant (FSTP)
AgencyState Department for Water and Sanitation
ProgramWater & Sanitation Development Project (WSDP)
Progress33.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start Date2021-11-05
Planned End DateN/A
Actual End DateN/A
ContractorWardy Communication Ltd
ConsultantBatch Associates Ltd JV Tertiary Consulting Engineers Ltd
Target AreasN/A
Scope of WorksRehabilitation of Kipevu Wastewater Treatment Plant and Pumping stations located at Mikindani, Miritini, JomvuScrew pump and PortReitz
ImpactsN/A
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 120,311,677.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 120,311,677.00
Cumulative ExpenditureKES 78,428,086.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 120,311,677.00

Beneficiaries

Target Households75,000
Target Population375,000