Galana Dam

Project Detail Report

Overview

StatusProposed
TypeDam
AgencyCoast Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksConstruction of 400 million cubic large rock Fill dam with impervious clay core
ImpactsN/A
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 50,000,000,000.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 50,000,000,000.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households7,500
Target Population37,500