Project Detail Report
| Status | Proposed |
|---|---|
| Type | Pipeline |
| Agency | Coast Water Works Development Agency |
| Program | GOK Funded Projects |
| Progress | 0.00% |
| County | N/A |
|---|---|
| Constituency | N/A |
| Ward | N/A |
| Setting | N/A |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Construction of a 98Km Canal, targeting to supply 136,000m3/ day |
| Impacts | N/A |
| Challenges | Feasibility Study Report Done by CWWDA & KWS, to proceed to Detailed designs, ESIA/RAP to establish the actual cost of the project. Upon completion the project will benefit 5,000 households along the canal and 200,000 livestock units |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 8,000,000,000.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 8,000,000,000.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Target Households | 5,000 |
|---|---|
| Target Population | 25,000 |