Overview
| Status | Proposed |
| Type | Sewer |
| Agency | Coast Water Works Development Agency |
| Program | GOK Funded Projects |
| Progress | 0.00% |
Location Information
| County | N/A |
| Constituency | N/A |
| Ward | N/A |
| Setting | N/A |
| Coordinates | , |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Construction of WWTP of capacity 4,600m3/d and 21Km of secondary and trunk sewerage pipelines diameter 225-450 mm |
| Impacts | N/A |
| Challenges | Preliminary designs ready
Upon completion 6,000 households will be connected |
| Remarks | N/A |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 100,000,000.00 |
| GoK Contract Sum | KES 100,000,000.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 6,000 |
| Target Population | 30,000 |