Supply of water to Ngomeni fish landing site

Project Detail Report

Overview

StatusCompleted
TypePipeline
AgencyCoast Water Works Development Agency
ProgramFOOD AND NUTRITION SECURITY
Progress100.00%

Location Information

CountyKilifi
ConstituencyMagarini
WardGongoni
SettingRural
Coordinates-3.078370, 40.141550

Timeline & Impact

Start Date2022-11-10
Planned End Date2023-09-04
Actual End DateN/A
ContractorEvernote Construction Ltd
ConsultantNone
Target AreasNgomeni fish landing site
Scope of WorksConstruction of 12km 160mm HDPE pipeline Construction of 6m High RC tower Supply and installation of 2, 10,000 litres plastic tank
ImpactsProvision of stable supply of water to Ngomeni Fish Landing site thus boosting their operations and the blue economy in general
ChallengesN/A
Remarkshanded over to MAWASCO

Project Cost

Total Contract Sum (GoK + Foreign)KES 49,600,179.00
GoK Contract SumKES 49,600,179.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 48,800,411.20
Outstanding CostKES 799,767.80

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved GOK 50,000,000.00

Beneficiaries

Target Households500
Target Population2,500