Construction of Watamu Sewerage System and Waste Water Treatment plant project

Project Detail Report

Overview

StatusProposed
TypeUnknown
AgencyCoast Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of Works• New Waste Water Treatment Plant (Waste Stabilization Ponds) comprising of Inlet Works, Anaerobic Ponds, Facultative Ponds, Maturation Ponds & Sludge Drying Beds • Reticulation 25 km sewer Sewerage Network within the service area of Watamu urban centre, Trunk Sewers connecting the Reticulation sewer with the New Waste Water Treatment Plant, pipeline sizes ranging between DN 150-450 • Sewage Pumping Stations at localized low points along the Sewerage Network, • Administration building with laboratory and Store, • Guard House and Grade 9 Staff Houses, • Associated Ancillary Works e.g. Access roads, water reticulation, drainage etc.
ImpactsN/A
ChallengesN/A
RemarksAwaiting Budgetary Allocation Upon completion 6,000 households will be connected

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,300,000,000.00
GoK Contract SumKES 1,300,000,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households1,200
Target Population6,000