Construction of Sewerage System and Waste Water Treatment Plant in Malindi Town, Kilifi County

Project Detail Report

Overview

StatusProposed
TypeUnknown
AgencyCoast Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksConstruction of 6,000m3/day Waste Water Treatment Plant which included 10Nr Ponds (Anaerobic, Primary Facultative , Secondary Facultative, Maturation) and 1Nr. Sludge Dryings beds, 10Nr pumping stations, construction of 44.5km sewer network including trunk and secondary sewers ranging from 100-600 mm diameter concrete, steel and uPVC pipelines, acquisition of Land for WWTP installation and household connection, construction of administration offices
ImpactsN/A
ChallengesN/A
RemarksAwaiting Budgetary Allocation Upon completion 17,000 households will be connected

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,800,000,000.00
GoK Contract SumKES 1,800,000,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households3,400
Target Population17,000