Mwatate, Dembwa, paranga dams

Project Detail Report

Overview

StatusProposed
TypeUnknown
AgencyCoast Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksEarth works,Pipelaying of assorted Classes and Sizes,Pumps,Power Houses,WTP Costructions and Equipments Installation
ImpactsAwaiting Budgetary Allocation Upon completion 50,000 households will be connected
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 7,300,000,000.00
GoK Contract SumKES 7,300,000,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households5,000
Target Population25,000