Construction of Taveta Sewerage System and Waste Water Treatment Plant-1.97 B

Project Detail Report

Overview

StatusProposed
TypeUnknown
AgencyCoast Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksNew waste water treatment plant Capacity 4,000m³/d.Construction of 225 – 370 mm Dia Trunk and secondary sewer pipelines of Approximate Total Length 73 km, 1 No pumping station.
ImpactsUpon completion 6,000 households will be connected
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,800,000,000.00
GoK Contract SumKES 1,800,000,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households1,200
Target Population6,000