Pipeline Replacement, Extension and Augmentation (Primary, secondary, tertiary & service mains), Bulk meters and consumer connections – Short-term phase (2017-2020) in Malindi & Gongoni

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyState Department for Water and Sanitation
ProgramWater & Sanitation Development Project (WSDP)
Progress96.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingUrban
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorYellow House Limited
ConsultantDesign Master Plan in JV with Studio Galli Ingegnera (SGI)
Target AreasN/A
Scope of WorksConstruction of new, replacement and upgrade of 31.7kms of primary & secondary pipeline mains, 52.7kms of tertiary lines, installation of 3,300no. New and replacement customer meters
Impacts>Protection of public health >Environmental preservation(through a Managed water supply system) >Access to Education for children especially girls >Economic benefits from employment (operation and maintenance staff) >Healthy and sustainable community due to improved quality of life >The WSP will also generate revenue from the water bills payments
Challenges>Cash flow challenges due to extended disbursement procedures
RemarksUpon completion 1650 households will be connected. Implemented by MAWASCO under WSDP

Project Cost

Total Contract Sum (GoK + Foreign)KES 707,773,817.50
GoK Contract SumKES 0.00
Foreign Contract SumKES 707,773,817.50
Cumulative ExpenditureKES 570,873,451.80
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 707,773,817.50

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 250,861,300.00
2022/23 Approved FOREIGN 282,989,500.00
2023/24 Approved FOREIGN 237,115,100.00
2024/25 Allocated FOREIGN 152,690,900.00

Beneficiaries

Target Households1,650
Target Population8,250