Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Ablution Blocks |
| Agency | State Department for Water and Sanitation |
| Program | Water & Sanitation Development Project (WSDP) |
| Progress | 56.00% |
| County | N/A |
|---|---|
| Constituency | N/A |
| Ward | N/A |
| Setting | N/A |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Groove View Limited - Terminated |
| Consultant | Runji Consulting Group Ltd |
| Target Areas | N/A |
| Scope of Works | Construction of 8 ablution blocks Eight (8) sites: Maungu, Voi Stadium, Caltex, Taveta Market, Bura Ndogo, Wundanyi and Bura |
| Impacts | N/A |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 90,013,167.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 90,013,167.00 |
| Cumulative Expenditure | KES 38,353,004.74 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Wb | Loan | 90,013,167.00 |
| Target Households | 200 |
|---|---|
| Target Population | 1,000 |