Dadaab Pipeline Extension

Project Detail Report

Overview

StatusOngoing
TypePipeline extension
AgencyState Department for Water and Sanitation
ProgramWater & Sanitation Development Project (WSDP)
Progress90.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start Date2022-02-06
Planned End DateN/A
Actual End DateN/A
ContractorBishin Transporters & Construction Co. Ltd
ConsultantRunji Consulting Group Ltd
Target AreasN/A
Scope of WorksRehabilitation of existing 4Number boreholes (Pump Replacement , Draw pipe replacement Solarization), Development of 2 Number new boreholes , Equipping & Solarization, Laying of pipe lines of various diameter & Cumulative length of 21km, Consumer metering, Construction of chlorinator house, Erection of Elevated steel water tanks
ImpactsN/A
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 178,859,035.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 178,859,035.00
Cumulative ExpenditureKES 111,552,182.10
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 178,859,035.00

Beneficiaries

Target Households12,000
Target Population60,000