Construction of 16No Communal on-site sanitation facilities

Project Detail Report

Overview

StatusOngoing
TypeAblution Blocks
AgencyState Department for Water and Sanitation
ProgramWater & Sanitation Development Project (WSDP)
Progress84.70%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorAmala Limited
ConsultantEast Africa Engineering Consultants Ltd JV Systel Enginering Ltd
Target AreasN/A
Scope of WorksConstruction of 16 Ablution blocks in Wajir Referral Hospital, Police line and KAPU lines, each connected to a septic tank and with shallow wells & 5,000L plastic Water tank.
ImpactsN/A
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 164,945,895.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 164,945,895.00
Cumulative ExpenditureKES 103,998,300.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 164,945,896.00

Beneficiaries

Target Households265
Target Population1,325