Completion of 8 ablution blocks 2 at Voi, 1 at Maungu, 2 at Wundanyi, 1 at Mwatate and 2 at Taveta.

Project Detail Report

Overview

StatusOngoing
TypeAblution Blocks
AgencyState Department for Water and Sanitation
ProgramWater & Sanitation Development Project (WSDP)
Progress2.00%

Location Information

CountyTaita-Taveta
ConstituencyWundanyi
WardWundanyi stadium, Wundanyi Market
SettingN/A
Coordinates-3.559139, 38.749958

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorJedel Enterprises - Current
ConsultantRunji Consulting Group Ltd
Target AreasVoi, Maungu, Taveta, Mwatate and Wundanyi
Scope of WorksConstruction of 8 ablution blocks Eight (8) sites: Maungu, Voi Stadium, Caltex, Taveta Market, Bura Ndogo, Wundanyi and Bura
ImpactsN/A
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 20,312,901.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 20,312,901.00
Cumulative ExpenditureKES 20,312,901.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Wb Loan 22,503,291.75

Beneficiaries

Target Households144
Target Population720