Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Rehabilitation of Water Supply |
| Progress | 100.00% |
| County | Kwale |
|---|---|
| Constituency | Lunga Lunga |
| Ward | Pongwe/Kikoneni |
| Setting | Rural |
| Coordinates | 0.325468, 36.433411 |
| Start Date | 2026-09-19 |
|---|---|
| Planned End Date | 2024-12-20 |
| Scope of Works | Equipping and Civil works |
| Impacts | Improve access to water |
| Challenges | No challenges |