Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Water Supply |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Rehabilitation of Water Supply |
| Progress | 100.00% |
| County | Kwale |
|---|---|
| Constituency | Lunga Lunga |
| Ward | Mwereni |
| Setting | Rural |
| Coordinates | -0.606010, 36.576275 |
| Start Date | 2024-06-27 |
|---|---|
| Planned End Date | 2024-09-28 |
| Scope of Works | Trench excavation and pipelaying 7km | Construction of 1 No CWP |
| Impacts | Improve access to water |
| Challenges | No challenges |