Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Rehabilitation of Water Supply |
| Progress | 100.00% |
| County | Kwale |
|---|---|
| Constituency | Matuga |
| Ward | Tsimba Golini |
| Setting | Rural |
| Coordinates | 0.475000, 35.850000 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Scope of Works | Drilling and Capping |
| Impacts | Improve access to water |
| Challenges | No challenges |