Kapsita (Mutate) Primary School Water Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyCentral Rift Valley Water Works Development Agency
ProgramGoK Directly Funded Projects
Progress100.00%

Location Information

CountyKwale
ConstituencyMatuga
WardKubo South
SettingRural
Coordinates-0.298259, 35.803484

Timeline & Impact

Start Date2024-05-24
Planned End Date2024-08-24
Scope of WorksDrilling, Equipping and Civil Works
ImpactsImprove access to water
ChallengesNo challenges