Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | GoK Directly Funded Projects |
| Progress | 0.00% |
| County | Kilifi |
|---|---|
| Constituency | Kilifi North |
| Ward | Kibarani |
| Setting | Rural |
| Coordinates | 0.805333, 35.695604 |
| Start Date | 2024-06-20 |
|---|---|
| Planned End Date | 2024-09-18 |
| Scope of Works | Drilling, Equipping and Civil Works |
| Impacts | Improve access to water |
| Challenges | No challenges |