Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Drainage |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | GoK Directly Funded Projects |
| Progress | 0.00% |
| County | Kilifi |
|---|---|
| Constituency | Kilifi North |
| Ward | Matsangoni |
| Setting | Rural |
| Coordinates | -0.840746, 36.477190 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Scope of Works | Construction of 220m road to the tank |
| Impacts | Improve access to water |
| Challenges | Require relocation of power lines before commencement of works |