Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Sewerage System |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP) |
| Progress | 100.00% |
| County | Mombasa |
|---|---|
| Constituency | Jomvu |
| Ward | Mikindani |
| Setting | Urban |
| Coordinates | -1.157011, 35.870514 |
| Start Date | 2019-04-15 |
|---|---|
| Planned End Date | 2021-01-12 |
| Scope of Works | Construction of RE’s Office; Secondary Sewers –length of 26.1km-; Trunk Sewers of 14.2 Km,,Main Trunk Sewers of 11Km,Sewage Treatment Works (3,000m3 Capacity)Last Mile Connectivity Works 81kms of pipe dia 50, 75, 110 and 160mm & 169Nr Concrete Valve chambers 2400 water connections and 500 sewer connections |
| Impacts | Improve access to water |
| Challenges | No challanges |