Completed
Water Pan
Approved
Wama WRUA
Marsabit · Saku · Sagante
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
04 Jan 2019
Planned End
01 Jan 2020
Actual End
07 Jan 2020
Contractor
Nothern Water Works Development Agency
Consultant
None
Location Type
Rural
Target Areas
Dukana
Scope of Works
Desilting and fencing of 40,000 m3 Dambala Gombo water pan
Impacts
Reduced silt deposit in the water pan
Key Challenges
COVID and floods delayed project
Remarks
Project Completed
GPS Coordinates
3.99762 37.27232
Funding Sources
Danida
🌍 Foreign
· Grant
KES 9.6M
Total
KES 9.6M
Beneficiaries
1,666
Households
8,330
Population
Technical Specs
Volume Abstracted
120.00 m³/day
Storage Reservoir
40,000.00 m³