Completed
Borehole
Approved
Awarsitu Pipeline Extension Water Project
Isiolo · Isiolo North · Awarsitu
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
-
Planned End
-
Actual End
-
Contractor
Isiolo Water and Sanitation Company
Consultant
None
Location Type
Rural
Target Areas
Isiolo North
Scope of Works
Preliminary activities, 8.5km rising main, Borehole pump and 50m3 masonry tank, accompanying measures
Impacts
Water accessibility to an additional 700 households
Key Challenges
Timeline was extended in the course of implementation due to delays
Remarks
Project Completed
GPS Coordinates
38.57488 1.02588
Funding Sources
Danida
🌍 Foreign
· Grant
KES 10.0M
Total
KES 10.0M
Beneficiaries
700
Households
3,500
Population
Technical Specs
Volume Abstracted
120.00 m³/day
Storage Reservoir
50.00 m³
Treated Water Mains
8.50 km
Distribution Lines
8.50 km
Created 16 Aug 2026, 14:25