Ongoing
Borehole
Approved
Laisamis Integrated Project
Marsabit · Laisamis · Laisamis
Overall Progress
50.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Start Date
12 Jul 2022
Planned End
-
Actual End
-
Contractor
Samsung limited
Consultant
None
Location Type
Rural
Target Areas
Olturot
Scope of Works
Rehabilitation of Olturot Water Supply, 4.0 km pipeline rehabilitation, rehabilitation of 4no Masonry tanks, 100m3 elevated steel tank, 2 NoWater Kiosk, 2 No Water troughs, rehabilitation of solar pumping systems and repair of fence. Springs intake works , CLTS 28 Villages, 2 no 3 door VIP latrine, 30,000m3 Water pan
Impacts
increased access to water and sanitation services in ASAL areas and resilience to climate change
Key Challenges
Political interference and low contrcator capacity.
Remarks
On-going project
GPS Coordinates
2.593256
37.081692
Funding Sources
Danida
🌍 Foreign
· Grant
KES 47.3M
Gok
🇰🇪 Domestic
· Grant
KES 2.2M
Total
KES 49.5M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Volume Abstracted
144.00 m³/day
Storage Reservoir
100.00 m³
Distribution Lines
3.03 km
Water Kiosks
2
Non-Sewered Sanitation Facilities
6