Ongoing
Borehole
Approved
Moyale Sub-county Integrated Project
Marsabit · Moyale · Sololo, Golbo and Rawana
Overall Progress
80.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Sustainable Management and Access to Water and Sanitation in the ASALs (SWASAP)
Start Date
12 Jul 2022
Planned End
-
Actual End
-
Contractor
Ms frontier Engenierring
Consultant
None
Location Type
Rural
Target Areas
sololo
Scope of Works
Repair of masonry tanks, rehabilitation of 2 No. Masonry and a 4.7 km pipeline extension, 2 No. 11KW solar system installation.2 No. Water Kiosk, 50m3 Elevated steel tank, 2 No. Water trough, CLTS in 30 Villages, 4 No 3 door VIP latrines, Desilting of a 30,000m3 water pan
Impacts
increased access to water and sanitation services in ASAL areas and resilience to climate change
Key Challenges
conflict betwwen the Gold miners and community.
Remarks
On-going project
GPS Coordinates
3.151128
39.250957
Funding Sources
Danida
🌍 Foreign
· Grant
KES 40.3M
Gok
🇰🇪 Domestic
· Grant
KES 1.3M
Total
KES 41.6M
Beneficiaries
1,300
Households
6,500
Population
Technical Specs
Volume Abstracted
192.00 m³/day
Storage Reservoir
100.00 m³
Distribution Lines
6.40 km
Water Kiosks
3
Non-Sewered Sanitation Facilities
12
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18