Completed
Berkads
Approved
Dahan WRUA
Mandera · Mandera West · Lagsure
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
-
Planned End
-
Actual End
-
Contractor
Dahan WRUA
Consultant
None
Location Type
Rural
Target Areas
Wangai Dahan
Scope of Works
Construction of 2 No.100 m3 Berkads.
Impacts
Serving additional for 1,320 residents in Wangai Dahan.
Key Challenges
Projecct delayed by irregularities in procurement that had to be remedied
Remarks
Project completed and operational
GPS Coordinates
3.393350 N 40.228740 E
Funding Sources
Danida
🌍 Foreign
· Grant
KES 4.9M
Total
KES 4.9M
Beneficiaries
183
Households
1,100
Population
Technical Specs
Volume Abstracted
12.00 m³/day
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18