Completed
Water Tanks
Approved
Lagha Tula WRUA
Tana River · Bura · Bangale
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Green Growth and Employment Programme (GGEP)
Start Date
-
Planned End
-
Actual End
-
Contractor
Lagha Tula WRUA
Consultant
None
Location Type
Rural
Target Areas
Bangale
Scope of Works
Installation and branding of 10 No. roof water harvesting tanks of 10 m3
Impacts
Additional service for 1,400 residents in Bangale area.
Key Challenges
Change of scope led to delays
Remarks
Project completed and operational
GPS Coordinates
0.6275911 39.2841307
Funding Sources
Danida
🌍 Foreign
· Grant
KES 2.8M
Total
KES 2.8M
Beneficiaries
194
Households
1,165
Population
Technical Specs
Storage Reservoir
10.00 m³
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18