Ongoing
Sanitation
Approved
Huluqho Reverse Osmosis Project
Garissa · Ijara · Huluqho
Overall Progress
45.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
GoK Priority Funding
Start Date
11 Jan 2021
Planned End
12 Jan 2022
Actual End
07 Aug 2023
Contractor
Drescoll Ltd
Consultant
None
Location Type
Rural
Target Areas
Huluqho centre, Hulugho primary school, KDF & AP camp
Scope of Works
Installation of 2 m3/hr Reverse Osmosis water treatment plant at Huluqho Girls Secondary School
Impacts
Once completed the project will serve 9800 people
Key Challenges
Project has audit issues and stalled
Remarks
Awaiting closure of audit by GAWASCO WSP issues to allow for final disbursement.
GPS Coordinates
1.14742 41.0514
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 13.2M
Total
KES 13.2M
Beneficiaries
300
Households
1,500
Population
Technical Specs
Volume Abstracted
16.00 m³/day
Treatment Capacity
16.00 m³/day
Storage Reservoir
50.00 m³
Treated Water Mains
4.00 km
Distribution Lines
6.00 km
Connections
4