Completed Pipeline extension Approved

Sabasaba Water Pipelines Rehab. Project

Murang'a · Maragua · Kamahuha

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
08 May 2024
Contractor
Johgab Construction Company Ltd
Consultant
None
Location Type
Urban
Target Areas
Sabasaba
Scope of Works
• 7.685 km Pipeline Extension • 300 no. Cold Water Consumer Meters •Construction of 2 no. Water Kiosks
Impacts
The project will enhance access to clean water for 2,215 people through a 7.685 km pipeline extension, 300 consumer meters for efficient water management, and two water kiosks to serve those without direct connections.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
-0.8767711 37.1430545
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 3.2M
Kfw
🌍 Foreign · Grant
KES 16.8M
Total KES 20.0M
Beneficiaries
443
Households
2,215
Population
Technical Specs
Storage Reservoir 10.00 m³
Treated Water Mains 7.69 km
Distribution Lines 7.69 km
Water Kiosks 2
Connections 300
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18