Completed Pipeline extension Approved

Ogango-Kasule Water Supply Augmentation Project

Kisumu · Kisumu East · Kolwa Central Ward

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Framoc Agencies Ltd
Consultant
None
Location Type
Urban
Target Areas
Ogango and Kasule
Scope of Works
• Construction of 2 no. water kiosks, • 100no. Cold Water Consumer Meters • 3.810 Km Pipeline Extensions
Impacts
The project will improve access to clean water for 12,226 people through a 3.810 km pipeline extension, 100 consumer meters for efficient water distribution, and two water kiosks to serve those without direct connections.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
-0.0779579 34.7896698
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 3.1M
Kfw
🌍 Foreign · Grant
KES 16.1M
Total KES 19.1M
Beneficiaries
2,445
Households
12,226
Population
Technical Specs
Storage Reservoir 10.00 m³
Treated Water Mains 3.81 km
Distribution Lines 3.81 km
Water Kiosks 2
Connections 100
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18