Completed Pipeline extension Approved

Gachuriri Water Supply Project

Embu · Mbeere South · Mbeti South Ward

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Fahimyasin Company, Framoc Agencies Limited, Tredak Limited and Edema Contractors Limited
Consultant
None
Location Type
Urban
Target Areas
Gachuriri
Scope of Works
• 14 km pipeline extension • Construction of 1 no. Closed kiosk • 200 no. Cold Water Consumer Meters • 1 no. 100 mm Master Meter
Impacts
The project will enhance water access for 5,695 people through a 14 km pipeline extension, 200 consumer meters for efficient distribution, a closed water kiosk for public access, and a 100 mm master meter for improved monitoring and management.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
-0.7102021 37.5175679
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 2.8M
Kfw
🌍 Foreign · Grant
KES 14.9M
Total KES 17.7M
Beneficiaries
1,139
Households
5,695
Population
Technical Specs
Storage Reservoir 5.00 m³
Treated Water Mains 14.00 km
Distribution Lines 14.00 km
Water Kiosks 1
Connections 200
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18