Completed
Pipeline extension
Approved
Augmenting Of Water Distribution Systems In Oljabet Town And Site Phase 2
Laikipia · Laikipia West · Githiga
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Joynary Engineering Company Ltd, Greenways International Company Ltd and Danco Capital Ltd
Consultant
None
Location Type
Urban
Target Areas
Nyahururu Oljabet
Scope of Works
• 17.14 km pipeline extension,
• 300 no. Cold Water Consumer Meters
Impacts
The project will improve water access for 9,000 people through a 17.14 km pipeline extension and 300 consumer meters, enhancing distribution efficiency and service reliability.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
0.1745592
36.3777082
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Kfw
🌍 Foreign
· Grant
KES 16.8M
Total
KES 20.0M
Beneficiaries
1,800
Households
9,000
Population
Technical Specs
Treated Water Mains
17.14 km
Distribution Lines
17.14 km
Connections
300