Ongoing
Pipeline extension
Approved
Border Point 1 Water Project
Mandera · Mandera East · Rhamu
Overall Progress
96.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
02 Jun 2025
Contractor
Tabarak Construction Limited
Consultant
None
Location Type
Urban
Target Areas
Border Point 1
Scope of Works
• 3.81km Pipeline extension
• 100m3 Elevated steel tank
• 4 no. Closed kiosks
Impacts
The project will enhance water access for 10,821 people through a 3.81 km pipeline extension, a 100m³ elevated steel tank for improved storage and supply, and four closed water kiosks to serve the community efficiently.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
none
GPS Coordinates
-0.5018056
37.0245810
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 2.8M
Kfw
🌍 Foreign
· Grant
KES 14.8M
Total
KES 17.7M
Beneficiaries
2,164
Households
10,821
Population
Technical Specs
Storage Reservoir
100.00 m³
Treated Water Mains
3.81 km
Distribution Lines
3.81 km
Water Kiosks
4