Ongoing
Pipeline extension
Approved
Kehancha Water Supply Project
Migori · Kuria West · Bukira East
Overall Progress
70.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Lemura Engineering Limited
Consultant
None
Location Type
Urban
Target Areas
Kehancha
Scope of Works
• 10,500m Pipeline extension
• 1 Unit of water pump set
• 500no. Consumer metres
• 1no. 12m High 100m3 elevated steel tank
• Fencing of tank area
Impacts
The project will enhance water access for 9,200 people through a 10.5 km pipeline extension, 500 consumer meters for efficient distribution, a 12m high 100m³ elevated steel tank for improved storage, a water pump set to boost supply, and fencing of the tank area for security.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
none
GPS Coordinates
-1.1991858
34.6161164
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Kfw
🌍 Foreign
· Grant
KES 16.7M
Total
KES 19.8M
Beneficiaries
1,840
Households
9,200
Population
Technical Specs
Storage Reservoir
100.00 m³
Treated Water Mains
10.50 km
Distribution Lines
10.50 km
Connections
500
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18