Ongoing
Pipeline extension
Approved
Saina Majengo Water Project
Kajiado · Kajiado Central · Majengo
Overall Progress
87.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Isginia Scandic Ltd
Consultant
None
Location Type
Urban
Target Areas
Kajiado
Scope of Works
• 10 km Pipeline extension,
• Construction of 1no. Closed kiosks,
• 103 no. Cold Water Consumer meters
• Construction of 150m3 elevated steel tank,
• Solarization unit for 1no. Borehole
Impacts
The project will enhance water access for 12,000 people through 103 consumer meters for efficient distribution.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
none
GPS Coordinates
-1.8277516
36.7907798
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Kfw
🌍 Foreign
· Grant
KES 16.6M
Total
KES 19.8M
Beneficiaries
2,400
Households
12,000
Population
Technical Specs
Storage Reservoir
150.00 m³
Treated Water Mains
10.00 km
Distribution Lines
10.00 km
Water Kiosks
1
Connections
103
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18