Report Back to Projects
Completed Pipeline extension Approved

Kihumbu-Ini Water Project

Murang'a · Gatanga · Kihumbu-Ini

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
10 Jun 2024
Contractor
Joghab Construction Company
Consultant
None
Location Type
Urban
Target Areas
Mabanda
Scope of Works
• 6.4 km pipeline extension • 1000no. Cold Water Consumer Meters
Impacts
The project will enhance water access for 8,292 people through a 6.4 km pipeline extension and 1,000 cold water consumer meters, ensuring efficient distribution and improved service delivery.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
-0.9301005 36.9815318
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 2.8M
Kfw
🌍 Foreign · Grant
KES 15.0M
Total KES 17.8M
Beneficiaries
1,658
Households
8,292
Population
Technical Specs
Storage Reservoir 6.40 m³
Treated Water Mains 6.40 km
Distribution Lines 6.40 km
Connections 100
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…