Completed
Pipeline extension
Approved
Kitikyumu-Malivani-Mwanzo Pipeline Extension Water Project
Makueni · Makueni · Wote/Nziu Wards
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Suwina Investment Ltd.
Consultant
None
Location Type
Urban
Target Areas
Maii
Scope of Works
• Construction of 1no.Closed kiosk
• 100.no. Cold Water Consumer Meters
• Pipeline Extensions by 7.833 km
• Construction of 1no. 100 m3 Masonry Tank
• Construction of 1no. 50m3 Elevated Steel Water Tank on 10m High Steel Tower
Impacts
The project will enhance water access for 6,245 people through 100 consumer meters for efficient distribution.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
Project completed and operational
GPS Coordinates
-1.7990373
37.5858910
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 2.7M
Kfw
🌍 Foreign
· Grant
KES 14.1M
Total
KES 16.8M
Beneficiaries
1,249
Households
6,245
Population
Technical Specs
Storage Reservoir
150.00 m³
Treated Water Mains
7.83 km
Distribution Lines
7.83 km
Water Kiosks
1
Connections
100
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18