Ongoing
Pipeline extension
Approved
Kasarani, Kaloleni & Matuiku Water Project
Nakuru · Molo · Elburgon
Overall Progress
89.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Heyinz Company Ltd and Noor Consult Ltd
Consultant
None
Location Type
Urban
Target Areas
Kasarani, Kaloleni, and Matuiku
Scope of Works
• 20km Pipeline extension
• 800no. 15mm volumetric meters
Impacts
The project will enhance water access for 5,490 people through a 20 km pipeline extension and 800 (15mm) volumetric meters, ensuring efficient water distribution and improved service delivery.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
-0.7105730
36.2944032
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.1M
Kfw
🌍 Foreign
· Grant
KES 16.5M
Total
KES 19.6M
Beneficiaries
1,098
Households
5,490
Population
Technical Specs
Treated Water Mains
20.00 km
Distribution Lines
20.00 km
Connections
800
Created 16 Aug 2026, 14:25
· Last updated 16 Aug 2026, 17:18