Ongoing
Water Supply
Approved
Oyugis Water Project
Homa Bay · Kasipul · Central Kasipul
Overall Progress
80.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
-
Contractor
Global Concretes & Construction Co.Ltd
Consultant
None
Location Type
Urban
Target Areas
Oyugis
Scope of Works
• 8.16km Pipeline extension
• 300no. 15mm Volumetric meters
Impacts
The project will enhance water access for 5,370 people through an 8.16 km pipeline extension and 300 (15mm) volumetric meters, ensuring efficient water distribution and improved service delivery.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
-0.5093130
34.7302293
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.2M
Kfw
🌍 Foreign
· Grant
KES 16.7M
Total
KES 19.8M
Beneficiaries
1,074
Households
5,370
Population
Technical Specs
Treated Water Mains
8.16 km
Distribution Lines
8.16 km
Connections
300