Report Back to Projects
Ongoing Pipeline extension Approved

Tarbaj Water Project

Wajir · Tarbaj · Tarbaj

Overall Progress
90.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
11 May 2024
Contractor
Ali Galo Traders Ltd
Consultant
None
Location Type
Urban
Target Areas
Tarbaj
Scope of Works
• 5.5 km Pipeline extension • 200 no. 15mm Volumetric meters • 2no. Water kiosks • 1no. Yard taps • 1no. Elevated steel tank 27m2
Impacts
The project will enhance water access for 24,300 people through a 5.5 km pipeline extension, 200 (15mm) volumetric meters for efficient distribution, two water kiosks and one yard tap for improved public access, and a 27m² elevated steel tank for reliable water storage and supply.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
2.2117143 40.1181672
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 2.8M
Kfw
🌍 Foreign · Grant
KES 14.6M
Total KES 17.3M
Beneficiaries
4,860
Households
24,300
Population
Technical Specs
Storage Reservoir 37.00 m³
Treated Water Mains 5.50 km
Distribution Lines 5.50 km
Water Kiosks 2
Connections 200
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18