Ongoing
Pipeline extension
Approved
Chuka/Karingani Water Infrustructure
Tharaka Nithi · Chuka/Igambang’ombe · Karingani
Overall Progress
90.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jun 2022
Planned End
04 Jun 2023
Actual End
04 Apr 2024
Contractor
Centura Limited
Consultant
None
Location Type
Urban
Target Areas
Chuka
Scope of Works
• 11.94km pipeline extension
• 720.no 15mm Volumetric metering
Impacts
The project will improve water access for 8,097 people through an 11.94 km pipeline extension and 720 (15mm) volumetric meters, ensuring efficient water distribution and enhanced service delivery.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
-0.3300623
37.6561184
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.0M
Kfw
🌍 Foreign
· Grant
KES 16.8M
Total
KES 19.9M
Beneficiaries
1,616
Households
8,079
Population
Technical Specs
Treated Water Mains
11.94 km
Distribution Lines
11.94 km
Water Kiosks
720
Connections
720