Ongoing
Pipeline extension
Approved
Kapsio Kariobangi water project
Elgeyo-Marakwet · Keiyo North · Kapsowar
Overall Progress
45.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Water Supply and Sanitation for the Urban Poor -KfW-Phase IV
Start Date
04 Jul 2022
Planned End
04 Jul 2023
Actual End
-
Contractor
Sinika Engineering Services Limited
Consultant
None
Location Type
Urban
Target Areas
Kapsio and Kariobangi
Scope of Works
• Construction of 1no. Closed kiosk
• 10 No. zonal meters and 150 No. consumer meters
• Pipeline extensions-14km
Impacts
The project will improve water access for 6,464 people through a 14 km pipeline extension, 10 zonal meters for network monitoring, 150 consumer meters for efficient distribution, and the construction of one closed kiosk for public access.
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
None
GPS Coordinates
0.6721651
35.5076672
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 3.1M
Kfw
🌍 Foreign
· Grant
KES 16.2M
Total
KES 19.3M
Beneficiaries
1,293
Households
6,464
Population
Technical Specs
Storage Reservoir
5.00 m³
Treated Water Mains
14.00 km
Distribution Lines
14.00 km
Water Kiosks
1
Connections
160