Completed
Borehole
Approved
Gongoni Marereni Water Project Phase I
Kilifi · Magarini · Gongoni marereni
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Start Date
-
Planned End
-
Actual End
-
Contractor
Century designs
Consultant
None
Location Type
Rural
Target Areas
Gongoni
Scope of Works
Preliminaries and general
Pipe works
New consumer connections
Water Kiosks (3No)
Contingency
Impacts
Improved access to clean water for more households
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
The project is complete and operational
GPS Coordinates
-2.9233024 40.138235
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 15.0M
Eu
🌍 Foreign
· Grant
KES 38.8M
Total
KES 53.8M
Beneficiaries
2,446
Households
12,230
Population
Technical Specs
Volume Abstracted
100.00 m³/day
Storage Reservoir
100.00 m³
Distribution Lines
12.80 km
Water Kiosks
3
Connections
50