Report Back to Projects
Completed Borehole Approved

Gongoni Marereni Water Project Phase I

Kilifi · Magarini · Gongoni marereni

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Start Date
-
Planned End
-
Actual End
-
Contractor
Century designs
Consultant
None
Location Type
Rural
Target Areas
Gongoni
Scope of Works
Preliminaries and general Pipe works New consumer connections Water Kiosks (3No) Contingency
Impacts
Improved access to clean water for more households
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
The project is complete and operational
GPS Coordinates
-2.9233024 40.138235
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 15.0M
Eu
🌍 Foreign · Grant
KES 38.8M
Total KES 53.8M
Beneficiaries
2,446
Households
12,230
Population
Technical Specs
Volume Abstracted 100.00 m³/day
Storage Reservoir 100.00 m³
Distribution Lines 12.80 km
Water Kiosks 3
Connections 50
Created 16 Aug 2026, 14:25 · Last updated 16 Aug 2026, 17:18