Augmentation of Kabarnet Water Supply Project

Baringo · Baringo Central · Kapropita, Kabarnet

Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Start Date
-
Planned End
-
Actual End
08 Apr 2024
Contractor
Century designs
Consultant
None
Location Type
Rural
Target Areas
Kapropita
Scope of Works
Magoini 1- 100m3 masonry tank, pump house, Fencing, 0.75kms pipeline, 15m3/hr chlorine doser, 22KW solarisation of the borehole.Magoini 2- Pump house, rehabilitation of 150m3 masonry tank, fencing, 0.9kms pipeline, 12m3/hr chlorine doser, 25KW Solarization of the borehole Kiboino- 100m3 masonry tank, 3.4kms pipeline , fencing, Automated water kiosk, 7.2km chlorine doser, 15.8 KW solarisation of th2e borehole Kisok- Rehabilitation of the pump house, rehabilitation and construction of the rising main, rehabilitation of 100m3 masonry tank, fencing works, automated water kiosk, 20m3/hr chlorine doser, solarisation of the boreholes Kabarnet- Solar booster system at Kabarnet
Impacts
Improved access to clean water for more households
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
The project is complete and operational
GPS Coordinates
0.4958163 35.7480137
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 9.1M
Eu
🌍 Foreign · Grant
KES 46.6M
Total KES 55.7M
Beneficiaries
2,500
Households
12,500
Population
Technical Specs
Volume Abstracted 100.00 m³/day
Storage Reservoir 100.00 m³
Distribution Lines 15.00 km
Water Kiosks 3
Connections 50