Completed
Borehole
Approved
Kaloleni Water supply
Taita-Taveta · Voi · Kaloleni
Overall Progress
100.00%
Project Overview
Implementing Agency
Water Sector Trust Fund
Programme
Ending Drought Emergencies - Support to drought Risk Management (EDE CPIRA)
Start Date
-
Planned End
-
Actual End
08 May 2024
Contractor
Lohim ltd
Consultant
None
Location Type
Rural
Target Areas
Kaloleni
Scope of Works
Construction of 1Nr concrete storage tank , Pipe works Construction of 2Nr cattle trough ,Pump station-improvement works Construction of ablution Block at kaloleni pumping station , Accompanying measures
Impacts
Improved access to clean water for more households
Key Challenges
Slow release GOK funds, Slow pace of construction
Remarks
The project is complete and operational
GPS Coordinates
-3.3868919671845057 38.57598803937435
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 17.0M
Eu
🌍 Foreign
· Grant
KES 53.0M
Total
KES 70.0M
Beneficiaries
4,702
Households
23,510
Population
Technical Specs
Volume Abstracted
100.00 m³/day
Storage Reservoir
100.00 m³
Distribution Lines
15.00 km
Water Kiosks
1
Connections
100